It might as well be spring. Currently there is a lot of activity on our construction sites througout the country.
In March alone, construction started on rooftop and ground-mounted projects with a total output of over 40 MWp.
Our teams therefore provide exciting insights into project implementation on a daily basis:
- Start of construction for a nearly 2.28 MWp open space in Großmehring. The drone images of project manager Willi Kreutzer-Sommerauer show that module assembly has already begun. In the Allgäu region, work started at the beginning of March on a rooftop project with just under 2MWp. What is particularly interesting here is that the electricity comes to the transformer via rails instead of the usual cables. The picture shows the current status of module installation on the south-facing shed roof.
- In Lower Bavaria, the transformer for an open space was delivered and installed yesterday. Site manager Kadir Akyön accompanied the action.
- On the construction site of the largest open space project in the Dachau district, we were able to count on ministerial support. Bavaria´s Deputy Minister President Hubert Aiwanger himself lent a hand during the pile driving of the substructure for the almost 19 MWp.
- The pile-driving work on field 4 of our milestone project in Bundorf is in full swing, reports project manager Enrico Makkay.